Public Sector BIM Adoption Timeline

BIM is part of the overall Government strategy to digitalise the construction sector by 2030.

Timeline

From January 2024 consultants engaged to design and oversee the construction of public works contracts with a value in excess of €100m will have Building Information Modelling (BIM) requirements included in their scope of service.

Over a period of 4 years these requirements will be extended to include the engagement of consultants and contractors down to projects with a value less than €1m.  At that point all public works projects will have BIM requirements incorporated.

The BIM adoption strategy utilises the buying power of the public sector which represents at least 25% of construction activity to incorporate digital delivery requirements as part of the overall Government strategy to digitalise the construction sector by 2030.

Table: Public Sector BIM Adoption Timeline

The timeline set out below is subject to review any changes will be based on feedback from our monitoring processes.

Month 0 = January 2024
Project Category Value Milestones Month

> 100 million

Milestone 1 – Design Team only

Month 0

> 100 million

Milestone 2 – Contractor and Supply Chain

Month 12

> 20 million

Milestone 3 - Design Team only

Month 12

> 20 million

Milestone 4 - Contractor and Supply Chain

Month 18

> 10 million

Milestone 5 - Design Team only

Month 18

> 10 million

Milestone 6 - Contractor and Supply Chain

Month 24

> 5 million

Milestone 7 - Design Team only

Month 30

> 5 million

Milestone 8 - Contractor and Supply Chain

Month 36

> 1 million

Milestone 9 - Design Team only

Month 36

> 1 million

Milestone 10 - Contractor and Supply Chain

Month 42

< 1 million

Milestone 11 - Design Team only

Month 42

< 1 million

Milestone 12 - Contractor and Supply Chain

Month 48